Fictional exampleSituation note · Payment platform migration
To: programme sponsor · Restricted circulation
MilestoneReported dateCredible dateWhat it depends on
Business acceptance testing complete15 March12 April · lateTest data sets delivered by the vendor before 1 March. They have not been ordered.
Partner flows cut over30 April28 May · lateTwo of seven partners have not started end-to-end testing.
Legacy system shut down30 June30 JuneAchievable if regulatory reporting moves to phase two.
Decisions requested from the 4 March steering committee
- Move regulatory reporting to phase two, or add two people to acceptance testing for six weeks.
- Escalate this week to the two late partners, at management level.
- Freeze scope changes from 1 April.